testimonials by pdh engineers
 
 

Recommended practice for the design of residential foundations

Quiz Questions:

   
1. An engineered foundation is defined as one for which design is based on three phases:
       
    geotechnical engineering information
    design of the foundation is performed by a licensed engineer
    construction is observed with written documentation
    All of the above
       
2. Prior to foundation design, geotechnical investigation and report should be completed by a geotechnical engineer.
       
    True
    False
       
3. Geotechnical reports should contain, as a minimum:
       
   

purpose and scope, authorization and limitations of services

   

investigative procedures

   

laboratory testing results

   

logs of borings and plan(s) showing boring locations

   

site characterization

   

foundation design information and recommendations

   

Professional Engineer's seal

   

All of the above

       
4. The geotechnical engineer shall characterize the site for design purposes. The report shall comment on site conditions, which may affect the foundation design, such as:
       
   

topography including drainage features and slopes

   

trees and other vegetation

   

seeps

   

stock tanks

   

fence lines or other linear features

   

All of the above

       
5. Deep Foundation (pier/pile) design information should include:
       
   

Bearing capacity and skin friction along the pier length

   

Pier types and depths, and bearing strata

   

Down drag effects on the piers

   

All of the above

       
6. What are the parameters required for Shallow foundations (including post and beam footings) design?
       
   

Bearing capacity and footing depth

   

Minimum bearing dimension

   

I & II

   

None of the above

       
7. The foundation design engineer shall obtain sufficient information for the design of the foundation.  This may include:
       
   

information gathered by a site visit

   

the subdivision plan, site plan or plat

   

the geotechnical report

   

all of the above

       
8. The plan shall require that a geotechnical engineer issue a summary report describing the methods, and results of investigation and testing that were used, and a statement that the existing or placed fills are suitable for support of a shallow soil-supported slab-on-ground, or that the foundation elements should penetrate the fill to undisturbed material.
       
   

True

   

False

       
9. The engineer's foundation plan and specifications should include:
       
   

descriptions of the reinforcing or pre-stressing cables and hardware;

   

concrete specifications including compressive strengths;

   

site preparation requirements;

   

notes concerning nearby existing or future vegetation and the required design

   

features to accommodate these conditions; and

   

the schedule of required construction observations and testing.

   

All of the above

       
10. At a minimum, foundations should be observed and tested as applicable to determine whether:
       
   

exposed sub grade soils are prepared in accordance with the plans and specifications;

   

fill material and placement are in accordance with the plans and specifications;

   

pier placement, size and depth meet plans and specifications;

   

foundation elements, including reinforcement, meet plans and specifications

   

immediately before concrete placement;

   

concrete properties and placement meet plans and specifications;

   

for post tension slabs, stressing meets the specified elongation and stressing load of

   

each tendon; and.

   

specified site grading and drainage has been constructed.

   

All of the above

       
11. At the satisfactory accomplishment of all the requirements of the plans and specifications, the engineer of record shall provide a letter to the client indicating, to the best of his knowledge the construction of the foundation was in substantial conformance with:
       
   

the minimum standards of practice presented in this document

   

the engineer's plans and specifications including any modifications or alterations authorized.

   

I & II

   

None of the above

       
12. Most problems resulting from expansive soils involve swelling or shrinking as evidenced by upward or downward movement of the foundation producing distress to the structure.
       
   

True

   

False

       
13. Engineered fill is that which has been designed by an engineer to act as a structural element of a constructed work and has been placed under engineering inspection, usually with density testing.
       
   

True

   

False

       
14. Select fill is composed of the material randomly found on the site, or imported to no particular specification, other than that it be free of debris and trash.
       
   

True

   

False

       
15. Foundations can experience downward movement as the result of the drying influence of nearby trees.
       
   

True

   

False

       
16. Forming fill is that which is typically used under residential foundation slabs and is variously known as sandy loam, river loam or fill dirt.
       
   

True

   

False

       
17. Uncontrolled fill is fill that has been determined to be unsuitable (or has not been proven suitable) to support a slab-on-ground foundation. Any fill that has not been approved by a qualified geotechnical engineer in writing shall be considered uncontrolled fill.
       
   

True

   

False

       
18. Pre-existing fill may be classified as engineered fill, after investigation by the geotechnical engineer. The approval may depend on the fill thickness, existence of trash and debris, the age of the fill, and the results of testing and proof rolling.
       
   

True

   

False

       
19. All laboratory testing shall be performed in general accordance with the American Society for Testing and Materials (ASTM) or other recognized standards.
       
   

True

   

False

       
20. Expansive clay is defined as soil having a weighted plasticity index greater than 15 as defined by Building Research Advisory Board (BRAB) or a maximum potential volume change greater than 1 percent.
       
   

True

   

False

       
   
 
 